Yale Pediatrics

United States Contractor News

Yale Pediatrics

United States Contractor News

How Draw Schedules and Progress Payments Actually Work on a Construction Project

Spread the love

A draw schedule breaks the total cost of a construction project into a series of payments, each tied to a specific point of progress. Instead of paying a contractor the full contract amount up front or waiting until the very end, the owner (or the bank, if a construction loan is involved) releases money in stages as work gets completed and verified. This protects everyone involved: the contractor gets paid for work actually finished, and the owner or lender avoids handing over cash for work that hasn’t happened yet.

On a typical home renovation or new build, a draw schedule might have five to ten draws. On a commercial project, it could have monthly draws tied to a percentage of completion rather than fixed milestones. Either way, the structure and the paperwork behind it matter as much as the dollar amounts.

Milestone-Based vs. Percentage-Based Draws

Most residential draw schedules are milestone-based. Payments are tied to visible, checkable stages of construction. A common five-draw structure for a new home might look like this:

  • Draw 1 (10%): Site work, permits, and foundation poured
  • Draw 2 (20%): Framing complete and dried in (roof and windows installed)
  • Draw 3 (25%): Rough mechanical, electrical, and plumbing complete
  • Draw 4 (25%): Drywall, interior trim, and cabinetry installed
  • Draw 5 (20%): Final finishes, punch list complete, certificate of occupancy issued

Commercial and larger multifamily projects often use percentage-of-completion draws instead. The contractor submits a monthly application for payment (commonly an AIA G702/G703 form) showing what percentage of each line item in the budget has been completed that month. A concrete subcontractor’s line item might show 60% complete in March and 100% complete in April, and the draw reflects the difference.

Who Approves the Draw

The approval chain depends on how the project is financed. On a cash-funded project, the owner or their architect reviews the work and signs off before releasing payment. On a financed project, a bank-appointed inspector (sometimes called a draw inspector or construction risk manager) visits the site, confirms the claimed work is actually in place, and reports back to the loan officer before funds are released.

This inspection step is where projects often slow down. A contractor might submit a draw request on the 25th of the month, but if the bank’s inspector can’t get out to the site until the following week, and the loan committee needs another few days to process the release, the contractor could be waiting two to three weeks for money tied to work already finished. Experienced contractors build this lag into their cash flow planning rather than assuming same-week payment.

Retainage: The Money Held Back Until the End

Most construction contracts include retainage, a percentage of each draw withheld until the project reaches substantial completion. Retainage typically runs 5% to 10% per draw. On a $500,000 project with 10% retainage, that means $50,000 doesn’t get paid out until the punch list is finished and the owner signs off.

Retainage exists to give the owner leverage to make sure a contractor finishes the small, tedious items at the end of a job rather than moving on to the next project once the big money has been paid. It’s also a frequent source of dispute. Contractors sometimes feel retainage gets held longer than the contract specifies, especially when punch list items drag out due to material delays or subcontractor scheduling rather than the general contractor’s performance. Reading the retainage terms in the contract before signing, including exactly what triggers release, saves a lot of frustration later.

Documentation That Makes or Breaks a Draw Request

A draw request that gets rejected or delayed almost always comes down to missing documentation. Lenders and owners typically want to see:

  • A completed AIA G702/G703 pay application or equivalent showing line-item progress
  • Lien waivers from the general contractor and any subcontractors or suppliers paid from the previous draw
  • Photos of the completed work, dated and organized by area or trade
  • Updated project schedule showing how actual progress compares to the original timeline
  • Invoices or receipts for materials purchased, if the draw includes material costs not yet installed

Lien waivers deserve particular attention. A conditional waiver says a subcontractor will release their lien rights once payment clears; an unconditional waiver says they’ve already been paid and give up those rights immediately. Banks and owners often require unconditional waivers from the prior draw before releasing the next one, which means a contractor needs to actually pay subcontractors promptly to keep the draw pipeline moving. A contractor who sits on subcontractor payments can end up stalling their own draw schedule.

What Happens When a Draw Falls Behind Schedule

Delays happen on almost every project, and a good draw schedule accounts for that rather than assuming a perfectly linear timeline. If a project is genuinely behind, the smart move is to communicate early rather than submitting a draw request that overstates progress. Inspectors and owners who catch a discrepancy between what’s billed and what’s actually built tend to scrutinize every future draw more closely, which slows down the entire remaining schedule.

If a delay is caused by something outside the contractor’s control, like a permit holdup, weather, or a material backorder, most standard contracts include a change order or schedule extension process to document the cause and adjust expectations without penalizing the contractor unfairly. Keeping a written log of delays as they happen, rather than trying to reconstruct the timeline later, makes this process far smoother.

Before signing a construction contract, ask for the specific draw schedule in writing, including dollar amounts or percentages tied to each milestone, the documentation required for each request, retainage terms, and the expected turnaround time between submission and payment. Getting these details spelled out before work begins prevents most of the disputes that show up midway through a project.

Related articles: New Construction vs. Buying an Existing Home: A Practical Cost and Timeline Comparison · How to Replace a Bathroom Faucet · Top 5 Reasons Homebuilders in Albany NY Use top rated General Contractors

How Draw Schedules and Progress Payments Actually Work on a Construction Project
Scroll to top